Watertown City Council Approves 10-Year Long-Term Capital Improvement Plan for 2027–2037

Northeast Radio SD News – Watertown, SD - The Watertown City Council voted Monday evening unanimously to accept and approve the city’s 10-Year Long-Term Capital Improvement Plan (CIP) covering planned equipment purchases, infrastructure upgrades, and debt service from 2027 through 2037.
During the Nov. 16 meeting, City Manager Alan Stager walked the council through the summary of the multi-year capital roadmap, which totals $155,183,840 in planned Fund 212 capital expenditures and $168,294,350 in projected capital revenues over the 11-year window shown in the schedule.
Conservative Revenue and Expense Projections
Stager emphasized that the long-term plan is intentionally built with conservative revenue estimates and higher inflation assumptions on equipment expenses to ensure the city stays within its means.
On the revenue side, the plan projects modest second-penny sales tax growth averaging 2.7% per year—starting at $11,747,330 in 2027 and rising to $15,787,420 by 2037, for a total of $150,457,350. State Transportation Program (STP) funds are budgeted to remain flat at $850,000 annually ($9,350,000 total), reflecting a state allocation that has not increased for at least the past five years. Interest income is projected at $8,031,320 across the plan based on the city’s cash reserve levels, alongside $455,680 in donations and contributions in 2027 for the Bramble Park Zoo bear habitat project.
Conversely, Stager noted that equipment cost projections factor in liberal inflation expectations—such as a 5% annual cost increase for police patrol vehicles—to prevent future budget shortfalls.
“We’re heavy on the expense side, light on the revenue side, so that we can ensure that we have a budget that we are able to work within here and provide the amenities that we need to provide our community,” Stager said.
Debt Service Ratio Expected to Drop by 2031
A key benchmark in the 2027–2037 CIP is the city’s debt-to-revenue ratio. Total debt service, fiscal agent charges, and capital lease payments account for $47,813,540 over the life of the plan, including $5,086,210 in 2027 and peaking at $5,578,250 in 2028.
Currently, existing debt service consumes 37% of CIP revenue in 2027 and 38% in 2028. Stager reminded the council that when the city previously issued bonds for the Prairie Lakes Ice Arena and recreation projects, officials anticipated a tight five-year window where debt payments would absorb nearly 40% of the capital budget.
According to the CIP schedule, that ratio drops to 35% in 2029, 34% in 2030, and 32% in 2031, before falling to 30% in 2034 and 16% by 2037 as major bonds are retired.
“We are right in the middle of that difficult five-year period of time,” Stager said. “But what you will see is when we get to 2031, and we start to come out of that, the amount of money that we will be able to reinvest into streets and street repair—perhaps at that time, the third fire station—we will be in a much better position to be able to do that as we start to pay down the debt.”
Departmental Capital Totals (2027–2037)
Across the city’s primary capital categories and enterprise funds, the 2027–2037 plan outlines the following multi-year totals:
· Public Works (Fund 212): $69,573,800 total, including $47,550,800 for street system improvements, $16,843,000 for machinery and equipment, $3,600,000 for storm sewer and flood control projects, $1,480,000 for cemetery improvements, and $100,000 for vehicles.
· Culture and Recreation (Fund 212): $21,526,250 total, including $13,964,500 for culture and recreation facility improvements, $4,301,500 for park and recreation equipment, $2,494,000 for Prairie Lakes Wellness Center facility improvements (highlighted by a $1,750,000 pool HVAC replacement in 2031), $716,250 for wellness center equipment, and $50,000 for park vehicles.
· Public Safety (Fund 212): $9,580,110 total, including $4,342,000 for fire and ambulance vehicles, $3,251,110 for police and E-911 vehicles, $1,040,000 for fire and ambulance equipment, $578,000 for police and E-911 equipment, and $369,000 for public safety facility improvements. In addition, the capital lease section includes a $2 million fire department ladder truck in 2028 financed over seven years at 5.5% interest ($352,000 annually through 2034, totaling $2,464,000).
· Operating Transfers Out (Fund 212): $5,583,250 total, including $3,521,180 in city matching transfers to the Airport Enterprise Fund, $2,000,000 to the E-911 Fund ($200,000 per year from 2027 through 2036), and $62,070 to Tax Increment Financing (TIF) #11 in 2027.
· Conservation and Development & General Government (Fund 212): $791,900 for industrial park and GIS mapping infrastructure, and $116,800 in 2027 for information technology security cameras and network hardware.
· Health and Welfare (Fund 212): $198,190 for animal control vehicles in 2030 ($80,000) and 2036 ($118,190).
· Enterprise Funds: $44,433,500 in total Airport Fund capital expenditures (backed by $37,951,130 in federal grants and $1,951,890 in state grants), $20,515,520 in Solid Waste Fund capital projects, and $8,410,475 in Wastewater Fund capital projects.
Lead Times and Council Discussion
Councilman Doug Allen made the motion to accept and approve the 10-year plan, and Councilman Brent Mohrmann seconded it.
During discussion, Allen noted that while he understands the need for a long-term roadmap, forecasting a full decade ahead can be challenging when economic conditions shift rapidly.
“Pretty hard to plan 10 years out—I mean, it’s a best guess,” Allen said. “I question how effective it is to do that because you’re really just adding percentages and making guesstimates at that. But I understand the need to do it. I mean, I think it’s good that we have a long-term plan, but I really do question how useful it is when so much changes in such a short period of time.”
Stager responded that extended manufacturing lead times on heavy municipal equipment make multi-year forecasting essential.
“Much of the equipment we buy has an extended lead time,” Stager said. “For example, another fire department in the state recently issued an order for a new fire apparatus at $1.2 million with a 55-month lead time. And in our plan, you’ll also see out there about 30 months from now is a purchase of a new ladder truck. It’s simply not possible to get much of this equipment if we’re not looking three to six years out. So it might seem like a decade is a long time, but on some of this it’s not.”
Following the discussion, the council voted 6-0 on a roll call vote in favor—to approve the 2027–2037 Capital Improvement Plan.